Elestaş Elektrik Üretim A.Ş.
Contact TR
Hamidiye GES
Home/ Power Plants/ Hamidiye Solar
Solar Solar power plant · Bolvadin / Afyon

Hamidiye Solar

Made up of 5 unlicensed solar plants on 77,650 m² of company-owned land at Hamidiye in Bolvadin, Afyonkarahisar, the site has an installed capacity of 5,337 kWp / 4.68 MWe. Using 20,140 Trina Solar photovoltaic modules and 95 KACO inverters, it was commissioned on 26 August 2016 as our first solar plant. Hamidiye generated 9,069 MWh in 2025, holds I-REC certificates and is going through Global Carbon Council (GCC) certification.

Project details

Company
Elestaş Elektrik Üretim A.Ş.
Plant name
Hamidiye Solar
Energy source
Solar
Licence no / date
—
Installed capacity
5.34 MWm / 4.68 MWe
Annual generation
9,069 MWh
Location
Bolvadin / Afyon
Commissioning date
26.08.2016
Hamidiye GES